Chrudim Ice Stadium

Operational Efficiency & Technical Performance

Installation Date: September 2023

  • Operating Adjustments: The existing ice was planed down by 1 cm, and the cooling temperature was increased by 0.5 °C.
  • Efficiency Gains: The time required for summer ice layer buildup was shortened by one-third.
  • Equipment Performance: Despite a warmer season, the stadium operated with only one compressor, leading to significant energy savings.
  • Current Stats: Ice thickness is maintained at 4.5 – 5 cm with a slab temperature of -5.5 °C.
Jan Makeš
Head of the Ice Stadium
Ice stadium Chrudim